There has been a comedy of errors in Lae road
designs including concrete pavements, a report released by Department
of Works (DoW) reveals.
The rehabilitation and upgrading of Lae City roads is
an on-going project consisting of various stages, with Stage 1 completed and
Stage 2 still in progress, and two projects under Stage 3 have commenced.
Dekenai Construction, East West 1, FTM Construction
and Lae Engineering procured four contracts for Stage 1 amounting to K24.4
million.
Shorncliffe, Dekenai Construction, Cameron
Construction, FTM Construction, East West 1 and R & Sons procured 12
contracts procured for Stage 2 amounting to K104.3 million plus variations.
“There was no proper design and engineer’s estimates
initially for all the contracts in Stage 1 and 2,” the report said.
“Also, the rates for existing contracts are quite
high.
“The initial scope of works is very poor.
“In some
contracts, bill of quantities (BOQs) is excessive while in others, total
opposite.
“Proper procurement process was bypassed to procure
these projects.
“The National Executive Council (NEC) condition of
contract is new.
“Most contractors are not familiar with this
condition of contract.
“The NEC conformed contract documents have major
irregularities and contradictions.
“Examples of such are the appointment and
responsibilities of the employer’s representative, the engineer/project manager
and the engineer’s representative/supervisor.
“This was not clearly spelt out in the agreement,
contract data and in the condition of contract.
“The option of concrete pavement is new in Papua New
Guinea.
“Very little or no detailed scope of works,
technical drawings, standard works, quality control management plan,
environmental management plan and traffic management plan were provided to the
contractors in Stages 1 and 2.
“This has delayed the completion of all the projects
and seriously impacted the quality of the finished concrete roads.
“Cost blow out is also evident due lack of technical
information.”
In stages 1 and 2, projects were managed by NME, Lae
City Authority and DOW at various stages and the employers’ representative was
Department of Finance (DoF)).
“DOW’s involvement was minimal or nil until August
2012,” the report said.
“These contracts were executed under certificates of
inexpediency (COI).
“Mismanagement of the projects under Stage 1 and 2
in design/construction and financial is evident.
“The government directed projects funds to the DOW
to manage and execute the remaining works under Stage 2.
“Stage 3 projects were awarded in August 2013.
“Contractors have mobilised on site and commenced
works.
“The cost of these two projects is K42million.
“Both projects are programmed to be completed in
June 2014.
“Works has commenced and in progress.”
No comments:
Post a Comment